Status of Cadre Review Proposals as on 31st July 2015
DoPT has published the Status of Cadre Review proposals processed in DoPT from 1st January, 2011 to 31st July 2015
Department of Personnel and Training has published the Status of Cadre Review proposals processed in DoPT from 1st January, 2011 to 31st July 2015
Status of Cadre Review proposals processed in DoPT from 1st January, 2011 to 31st July 2015
A. Approved by Cabinet
S.No. | Name of the Service | CRC* Meeting | Cabinet Approval |
1. | CPWD Central Engineering-Service, Central Electrical Mechanical Engineering Service and Central Architecture Service | 27/06/2011 | 03/01/2012 |
2. | Military Engineering Services (Indian Defence Service of Engineers, Architect Cadre and Surveyor Cadre) | 22/09/2011 and 23/01/2012 | 18/04/2013 |
3. | Indian Radio Regulatory Service | 19/02/2013 | 03/07/2013 |
4. | Indian Revenue Service | 19/02/2013 and GoM** on 29/04/2013 | 23/05/2013 |
5. | Indian Customs & Central Excise | 27/08/2013 | 05/12/2013 |
6. | Indian Cost Accounts Service | 29/10/2013 | 02/01/2014 |
7. | Central Labour Service | 19/02/2013 | 17/07/2013 |
8. | Central Power Engineering Service | 11/12/2013 | 13/05/2014 |
9. | Indian Ordnance Factory Service | 19/03/2014 | 29/10/2014 |
10. | Indian Civil Accounts Service | 17/07/2013 | 16/01/2015 |
11. | Border Road Engineering Service | 26/02/2015 | 07/04/2015 |
12. | Defence Aeronautical Quality Assurance Service | 08/01/2015 | 06/05/2015 |
13. | Indian Trade Service | 06/05/2014 | 01/07/2015 |
14. | Indian Statistical Service | 24/06/2014 | 29/07/2015*** |
*CRC – Cadre Review Committee ** GoM – Group of Ministers *** Minutes awaited
B. Pending Proposals
Sl. No. | Name of the Service | Status |
(i) With Cadre Controlling Authority/Ministry Concerned – CRC meeting held but Cabinet approval pending (4) |
||
1. | Railway Protection Force | Â CRC meeting held on 29/07/2013. Decision with the approval of Mos (PP) and FM has been communicated to the Ministry of Railways on 09/10/2013 for taking Cabinet approval. |
2, | Indian Naval Material | The CRC meeting held on 24/10/2013. Comments of DoPT on Cabinet Note have been provided on 21st January, 2015. |
3. | Â Indian Information Service | CRC meeting held on 30/07/2014. Approval of MoS (PP) and FM has been conveyed to Ministry of Information & Broadcasting for taking Cabinet approval on 15/12/2014. |
4. | DGET & Women Training Directorate | CRC Meeting held on 10/04/2015. Approval of MoS (PP) and FM Directorate has been conveyed to Ministry of Labour & Employment for taking Cabinet approval on 26/05/2015. |
(ii) With Cabinet Secretariat (3) |
||
5. | Ministry of Micro, Small and Medium Enterprises MSME | Approval of Secretary (P) & Secretary (Exp) has been obtained and the Note for Cadre Review Committee has been sent to Cabinet Secretariat |
6. | Indian Postal Service | The first CRC Meeting was held on 20/07/2015. It was decided that the Cadre review proposals may be taken after the report of 7th Pay Commission is received. |
7. | Indian P&T Acctt. and Fin. Service | Approval of Secretary (Expenditure) on the revised cadre strength has been obtained and Note for Cadre Review Committee has been sent to cabinet Sectt. on 27/07/2015. |
(iii) With Department of Personnel & Training (10) |
||
8. | Central Reserve Police Force | The-cadre structure is under submission in view of discussion held in meeting with MHA on 08/07/2015 and 17/07/2015 |
9. | Central Engineering Service (Roads) | The Proposal was received on 24/04/2014.Clarifications were sought from MoRTH, and based on reply received on 16/10/2014 a revised structure was proposed and sent to MoRTH for their comments. The proposal has been referred by the DoE with their comments on 26/06/2015. A meeting is scheduled to be held on 14/08/2015. |
10. | Indian Railways Personnel Service | Comments of DoE on Work Charge posts have been received and the same is under submission. |
11. | Indian Railways Accounts Service | Comments of DoE on Work Charge posts have been received andthe same is under examination. |
12. | Indian Railways Stores Service |
-do- |
13. |  Indian Railways Service of Signal Engineers |
-do- |
14. | Indian Railways Service of Electrical Engineers |
-do- |
15. | Â Indian Railways Traffic Service |
-do- |
16. | Indian Railways Service of Mechanical Engineers |
-do- |
17. | Indian Railways Service of Engineers |
-do- |
(iv) With Ministry concerned for clarifications (3) |
||
18. | Indian P&T Building Works | Clarifications are awaited from DoT. |
19. | Indian Telecom Service | Proposal-received on 13/05/2015. A meeting was held under the Chairmanship of Secretary (P) on 05/06/2015 and the DoT was asked to clarify certain issues. Reply from DoT is awaited. |
20. | Indian Defence Accounts Service | Proposal received on 22/05/2015. Clarification has been sought vide letter dated 23/06/2015. Reply from M/o Defence is awaited. |
Note: 1. In all the remaining cadres. letters have been written to the Cadre Controlling Authorities to send the cadre review proposals for the services/cadres pertaining to their departments.
2. By letter dated 20/04/2015 suggestions have been invited from the cadre Controlling Authorities on Cadre Review on email id [email protected]
3. A presentation dated 19/12/2014 on “Reforming Personnel management in Gujarat “has been uploaded on the site for information as it contains many new initiatives of the Government of Gujarat. Slide number 16-47 has the details of restructuring and the recruitment calendar. The link is http://persmin.gov.in/DOPT/CSWing/CRDivision/HRReforms_Guj.pdf.